Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

单选题
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

Ascope statement

Bactivity list

Cproject charter

Dproject schedule