单选题

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

Ascope statement

Bactivity list

Cproject charter

Dproject schedule

正确答案:A (备注:此答案有误)

相似试题

  • 单选题

    Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress.

    答案解析

  • 单选题

    Developing the project schedule is often aniterative process. It determines the planned start and finish dates for projectactivities and milestones. Schedule development can require the review andrevision of duration estimates and resource estimates to create an approvedproject schedule that can serve as a baseline to ( ) progress.A.analyze

    答案解析

  • 单选题

    Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

    答案解析

  • 单选题

    Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).A.fast tracking

    答案解析

  • 单选题

    Schedule the check of the tires at regular intervals

    答案解析

热门题库