Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ( ) progress. A.analyze

单选题
Developing the project schedule is often an
iterative process. It determines the planned start and finish dates for project
activities and milestones. Schedule development can require the review and
revision of duration estimates and resource estimates to create an approved
project schedule that can serve as a baseline to (  ) progress.
A.analyze 

Atrack

Blevel

Cexten