Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

Aactivity duration estimating, schedule developing, activity resource estimating

Bactivity resource estimating, activity duration estimating, schedule development

Cschedule developing, activity resource estimating, activity duration estimating

Dactivity resource estimating, schedule developing, activity duration estimating

正确答案:A (备注:此答案有误)

相似试题

  • 单选题

    Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).A.fast tracking

    答案解析

  • 单选题

    Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .

    答案解析

  • 单选题

    Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

    答案解析

  • 单选题

    Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT

    答案解析

  • 单选题

    A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.

    答案解析

热门题库