单选题

The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .

Ahe project is ahead of its planned schedule

Bless work was completed than was planned t

Cthe cost overrun for work completed

Dthe cost underrun of performance to date

正确答案:A (备注:此答案有误)