A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear on the chart ( ) .

A4 weeks

B5 weeks

C6 weeks

D7 weeks

正确答案:A (备注:此答案有误)