The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The project manager maintains this link through()

单选题
The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The project manager maintains this link through()

APeriodic project reports, periodic visits to the customer, and telephonic exchanges

BSubordinates, project team members, and the project sponsor

COne-time reports, weekly reports, and monthly reports

DThe telephone, facsimile, and data transmission