The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality), ( ), and cost

Aresource

Btime

Cplan

Dtool

正确答案:A (备注:此答案有误)

相似试题

  • 单选题

    Risk management allows the project manager and the project team not to()

    答案解析

  • 单选题

    The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The project manager maintains this link through()

    答案解析

  • 单选题

    The project team____people from different departments of the country.(2.0)

    答案解析

  • 单选题

    Project manager believes that modifying the project scope may provide added value for the customer. The project manager should ( ) .A.change the scope baseline

    答案解析

  • 单选题

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is()