单选题

Before a project schedule can be created,the schedule maker should have a ( ) ,an effort estimate for each task,and a resource list with availability for each resource.

Awork breakdown structure

Bbaseline

Csoftware requirements specification

Dplan

正确答案:A (备注:此答案有误)