Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource

单选题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. 
A.independent resource

Aindividual work loa

Cwork milestone

Dwork package