In the process of communication requirement analysis,the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law,a project with 10 stakeholders has ( ) potential communication channels.

单选题
In the process of communication requirement analysis,the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law,a project with 10 stakeholders has ( ) potential communication channels.

A10

B45

C50

D100