Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).

AFinish-to-Start

BFinish-to-Finish

CStart-to-Start

DStart-to-Finish

正确答案:A (备注:此答案有误)